N.M. Code R. § 1.5.7.8
B. The determination shall include consideration of the following criteria:
(1) the extent to which the project requirements have been, or can be, adequately defined;
(2) time constraints for delivery of the project;
(3) the capability, experience and availability of potential offerors familiar with the design and build process;
(4) the suitability of the project for use of the design and build process as concerns time, schedule, costs, and quality; and
(5) the capability of the using agency to manage the project, including experienced personnel or outside consultants, and to oversee the project with persons who are familiar with the design and build process.
C. It is recommended that determination also include consideration of:
(1) budget constraints;
(2) the desirability of alternative designs;
(3) the need or desirability for a single point of accountability;
(4) the desirability to use specialized services for the project;
(5) the availability of design and build teams; and
(6) other factors as may be documented with facts by the using body.
[4-15-98; Recompiled 11/30/01]