- (a) Except as specified in (c), below, it shall be the responsibility of the well owner to have an abandoned well sealed.
- (b) Upon completing a replacement well installation, a licensed water well contractor shall inform the well owner of the requirements of We 603 and We 604, pertaining to maintenance and abandonment of the existing well.
(c) A licensed water well contractor shall be responsible for sealing:
- (1) A failed borehole, or
(2) An abandoned well if the abandonment:
- a. Resulted from improper well construction, and
- b. Occurred within 12 months of the date of construction.
Source. (See Revision Note at chapter heading for We 600) #12083 eff 3-1-17