N.H. Code Admin. R. Puc 904.04
Application Completeness Review
Effective Sep 14, 2020#7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09 New. #9515, eff 7-18-09; ss by #9998, eff 9-20-11; ss by #13080, eff 9-14-20Public Utilities Commission
- (a) The interconnection process shall be deemed to have commenced when the customer-generator submits a complete application pursuant to this part.
- (b) The distribution utility shall evaluate the application for completeness and notify the customer-generator in writing within 10 business days of the application’s receipt whether the application is or is not complete and, if the application is not complete, inform the customer-generator in writing of any information required to be provided to complete the application.
- (c) The distribution utility shall verify that the customer-generator’s facility equipment meets the requirements of Puc 905.
- (d) If the distribution utility approves the application, the distribution utility shall sign the application and return the approved application to the customer-generator.
- (e) If the distribution utility determines that interconnection of the customer-generator’s facility would jeopardize the safety, reliability, or power quality of the local distribution system, the distribution utility shall require the customer-generator to pay for necessary modifications to the distribution system before the application is approved.
- (f) In the event that the distribution utility requires the customer-generator to pay for system modifications pursuant to (e) above, the distribution utility shall provide to the customer-generator a description of work and an estimate of the cost to complete that work.
- (g) If the customer-generator agrees to pay for the system modifications, the customer-generator shall sign the description of the work and submit a signed copy and the payment of the estimated costs to the distribution utility.
- (h) Upon receipt of the customer-generator’s approval and payment, the distribution utility shall perform the system modifications.
- (i) Upon completion of the system modifications, the distribution utility shall sign the application approval and provide a copy of the signed approval to the customer-generator.
Source. #7424, eff 1-12-01; ss by #9353, INTERIM, eff 1-12-09, EXPIRED: 7-11-09 New. #9515, eff 7-18-09; ss by #9998, eff 9-20-11; ss by #13080, eff 9-14-20