- (a) The department shall process the “Application for Conditional Approval to Operate a Crematory” in accordance with RSA 541-A:29.
- (b) Once an application is received the department shall schedule an inspection of the crematory pursuant to He-P 701.07.
- (c) The department shall grant conditional approval to operate a newly constructed crematory following a successful inspection as described in He-P 701.07(c).
(d) If a conditional approval is granted, the department shall:
- (1) Notify the applicant in writing of conditional approval to perform cremations for 90 days; and
- (2) Schedule an inspection of the crematory as described in to He-P 701.07(a)(2).
(e) If a conditional approval is denied, the department shall notify the applicant in writing of:
- (1) The reason for the denial; and
- (2) Any deficiencies listed in the inspection report described in He-P 701.07(d).
- (f) The department shall notify the applicant in writing of unconditional approval to operate a crematory following a successful inspection as described in He-P 701.07(a)(2).
Source. (See Revision Note at chapter heading for He-P 700) #8480, eff 11-5-05, EXPIRED: 11-5-13