The project-specific information required by Env-Wt 310.01(c)(1) or Env-Wt 311.03(b)(11), as applicable, for a dredge project shall be as follows:
(a) A description of the material and area to be dredged, including:
- (1) The volume of material to be dredged, in cubic yards for projects in public waters;
- (2) The square footage of the area to be dredged for non-public waters or wetlands;
- (3) The type of material to be dredged; and
- (4) Whether any invasive species are present;
- (b) The erosion and sediment control measures proposed to be used;
- (c) The methods proposed to dewater the dredged material;
- (d) The location at which dewatering will occur;
- (e) The equipment proposed to perform the dredging;
- (f) The proposed disposal site;
- (g) Identification of all known potential sources of soil or water contamination;
- (h) If potential sources are documented in (g), above, the method of sampling for contaminants and a plan to manage contaminated materials;
- (i) A description of how dredged material will be contained during the dredging process; and
- (j) An explanation of the timing of the project and how such timing helps minimize impacts on aquatic resources.
Source. #12805, eff 12-15-19