(a) Work may be done under utility SPN only if:
- (1) The project meets the minimum impact criteria in Env-Wt 521.06(a);
(2) The project has only:
- a. Temporary impacts associated with inspections, maintenance, and repair of existing utility assets and rights of way; and
- b. Less than 3,000 SF of permanent impacts for replacement of utility assets; and
- (3) The project proponent agrees to follow the Utility BMPs, available as noted in Appendix B.
(b) Work shall not be done under a utility SPN if the project:
- (1) Establishes one or more new permanent access roads in jurisdictional areas;
- (2) Installs one or more permanent crossings of streams or wetlands, or both;
- (3) Constructs one or more new utility corridors or rights-of-way;
- (4) Installs new utility assets within existing utility corridors or rights-of-way;
- (5) Does not meet the standard conditions in Env-Wt 307; or
- (6) Otherwise exceeds the minimum impact criteria.
Source. #12805, eff 12-15-19