(a) The maintenance and repair of a boathouse or dug-in basin shall be a minimum impact project only if all of the following criteria are met:
- (1) There is no change in the height, footprint, location, or configuration of the existing structures;
- (2) The boathouse and any associated docking structures are existing legal structures;
- (3) Where the structure is subject to RSA 482-A:26, the requirements and limitations of RSA 482-A:26 are fully met; and
- (4) No material will be dredged from areas that were flowed over by public waters.
(b) The maintenance and repair of a boathouse or dug-in basin shall be a minor impact project only if all of the following criteria are met:
- (1) There is no increase in the height or area of, or number of slips provided by, the existing structures;
- (2) The boathouse and any associated docking structures are existing legal structures;
- (3) Where the structure is subject to RSA 482-A:26, the requirements and limitations of RSA 482-A:26 are fully met; and
- (4) Not more than 20 CY of material will be dredged from areas that were flowed over by public waters.
- (c) The maintenance and repair of any boathouse or dug-in basin that fails to meet the criteria of (a) or (b), above, shall be a major impact project.
Source. #12805, eff 12-15-19; ss by #13776, eff 10-13-23; ss by #14389, eff 9-25-25, EXPIRES: 9-25-35