(a) For projects to remove NAV or to remove or otherwise control EAW that are not exempt under Env-Wt 510.03, the project-specific information required by Env-Wt 310.01(c)(1) or Env-Wt 311.03(b)(11), as applicable, shall be as follows:
(1) A brief summary of the proposed project, including:
- a. A concise statement of what the project is intended to accomplish;
- b. A list of each task to be undertaken as part of the project and for each, who will do it and how it will be done;
- c. The location of the proposed project and the name of each owner of property adjacent to the project;
- d. The proposed start date and end date of the project;
- e. A description of each target plant species for removal; and
- f. An estimate of the total footprint area in square feet (SF) and volume of vegetation in cubic yards (CY) to be removed and non-target species in the vicinity;
(2) For any EAW removal project proposing more than 10,000 SF in surface area, more than 5% of the surface area of a waterbody, or any impact to a PRA, an aquatic vegetation management plan for the impacted area of the lake or pond that:
- a. Addresses long-term and cumulative impacts from the proposed project; and
b. Identifies:
- 1. The functional value of the vegetation to be removed; and
- 2. Known circumstances that caused the increase in sediments or nutrients to the proposed impact area;
(3) A plan showing the proposed areas for NAV or EAW removal, as applicable, with a listing and annotation showing information on species abundance and coverage including:
- a. Description of plant species to be removed and description of the plant community;
- b. The extent of areal coverage;
- c. The potential impact on native plant communities, if applicable, and the distance of those native plant communities from existing docking facilities;
- d. Detailed dimensions showing the existing vegetative cover and the proposed removal area of NAV or EAW removal; and
- e. The depth of removal;
(4) A description of the proposed control methods and the justification for the method selected, including:
- a. Methods to contain, control, and minimize water quality impacts;
- b. Methods to transfer vegetation that is removed without dispersing it;
- c. Method(s) and location(s) for dewatering removed vegetation;
- d. Methods to minimize impacts to fishery and wildlife habitats based on the time of year the project will occur; and
- e. Method of disposal of EAW, consistent with Env-Wq 1303.06 relative to acceptable means of disposal; and
- (5) For projects that propose mechanical harvesting of EAW from areas less than 2 meters deep, equivalent to 6.6 feet deep, or for which an aquatic vegetation management plan is required by (2), above, a wetland delineation, wetland assessment, and characterization of emergent aquatic bed wetlands.
- (b) The applicant shall provide copies of the plan required by (a)(2) to the local lake association and conservation commission(s).
Source. #12805, eff 12-15-19; amd by 13124, eff 10-23-20