N.H. Code Admin. R. Env-Wr 404.03
Conditions of Permit
Effective May 24, 2024#1716, eff 2-20-81; ss by #2207, eff 12-13-82; ss by #2900, eff 11-7-84, EXPIRED 11-7-90 New. #5080, eff 2-22-91; rpld by #6462-B, eff 2-21-97 New. #8414, eff 8-20-0; ss by #10510, eff 1-22-14; ss by #13980, eff 5-24-24Dam-Related Programs
The following conditions shall apply to all permits to construct or reconstruct a dam:
- (a) The permit shall be valid for 5 years from the date of issuance;
- (b) Work under the permit shall be completed within 5 years unless the owner has requested and received a time extension in accordance with Env-Wr 404.04;
- (c) All work on the dam shall comply with the approved plans and specifications, subject to design changes approved and documented in accordance with Env-Wr 404.05;
- (d) The engineer shall provide a final inspection report in accordance with Env-Wr 405.07;
- (e) The engineer shall certify to the department that the work was completed in accordance with the approved plans and specification and design intent as required by Env-Wr 405.08;
- (f) Inspections shall be performed in accordance with the plan submitted pursuant to Env-Wr 405.04;
- (g) The owner shall notify the department upon completion of the work in accordance with Env-Wr 405.10(a);
- (h) The owner shall maintain a current mailing and email address with the department;
- (i) The owner shall operate and maintain the structure in accordance with the written approved OMRF procedures submitted in accordance with Env-Wr 402.06(a)(8); and
- (j) The department shall include in the permit any other conditions necessary to ensure protection of public safety that are based on the specific design, site, and watershed.
Source. #1716, eff 2-20-81; ss by #2207, eff 12-13-82; ss by #2900, eff 11-7-84, EXPIRED 11-7-90 New. #5080, eff 2-22-91; rpld by #6462-B, eff 2-21-97 New. #8414, eff 8-20-0; ss by #10510, eff 1-22-14; ss by #13980, eff 5-24-24