For life cycle comparison of treatment technology options, the basis of design report shall include a description or analysis of:
- (a) Capital, operation, and maintenance costs, including energy costs;
- (b) Life cycle comparison over a 20-year planning period unless an alternative length planning period is justified;
- (c) Discount rates, based on the discount rate set forth in Appendix C of OMB circular A-94 available at https://www.whitehouse.gov/wp-content/uploads/2023/12/CircularA-94AppendixC.pdf;
- (d) Present worth analysis using total project cost including construction and non-construction costs;
- (e) Average annual operation and maintenance costs over the life of the project, converted to present day dollars using a uniform series present worth calculation;
- (f) Deductions of the present worth of the salvage value;
- (g) Net present value calculations for each evaluated treatment technology option; and
(h) Non-economic factors such as social and environmental aspects, including, but not limited to:
- (1) Reliability;
- (2) Operational complexity;
- (3) Expandability; and
- (4) Sustainability.
Source. (See Revision Note at chapter heading for Env-Wq 700) #8590, eff 3-25-06; ss by #10693, eff 10-15-14; ss by #14258, eff 7-1-25, EXPIRES: 7-1-35