- (a) Pursuant to RSA 485-A:4, IX, the applicant shall submit plans and specifications for wastewater facilities for review and approval in accordance with Env-Wq 700.
- (b) For projects to abate NPS pollution, the applicant shall submit plans and specifications that meet the applicable requirements of Env-Wq 1503.07 through Env-Wq 1503.09 and demonstrate compliance with the applicable provisions of Env-Wq 1508.
- (c) For dam removal and repair projects, the applicant shall submit plans and specifications that meet the applicable requirements of Env-Wr 100 through Env-Wr 600.
- (d) For subdivision and individual sewage disposal system projects, the applicant shall submit plans and specifications that meet the applicable requirements of Env-Wq 1000.
Source. (See Revision Notes #1-#3 at chapter heading for Env-Wq 500) #10984, eff 12-1-15; ss by #13511, eff 12-20-22