- (a) For projects that do not qualify for a CE, the department shall prepare an EA in accordance with this section.
(b) The EA shall contain the following information:
- (1) The purpose of and need for the proposed project;
- (2) A list of all environmental concerns raised by the proposed project;
- (3) A list of alternatives to the proposed project, including a no action alternative;
(4) Details of the recommended action, which shall be the proposed project or an alternative identified in the planning document prepared pursuant to Env-Wq 506.05(a) or (b), as applicable, that:
- a. Is most likely to ensure compliance with federal and state water quality requirements over the projected life of the funded infrastructure; and
- b. Best meets the criteria specified in Env-Wq 505.02(a)(1); and
- (5) Mitigation measures required for the recommended action, if any.
- (c) The department shall forward the EA to the applicant to distribute for review and comment in accordance with Env-Wq 508.05.
Source. (See Revision Notes #1-#3 at chapter heading for Env-Wq 500) #10984, eff 12-1-15; ss by #13511, eff 12-20-22