N.H. Code Admin. R. Env-Wq 2302.18
“Excusable delay” means a delay that is beyond the recipient’s control in beginning or completing the planning, design, construction, or implementation of a project, such as a delay caused by an act of nature or war.
Source. #13858, INTERIM, eff 1-27-24, EXPIRED: 7-25-24 New. #14078, eff 9-24-24