- (a) If the application contains everything required by Env-Wq 1512.04, the department shall assign the application a file number and provide written notification within 14 days to the applicant that their PBN is complete.
- (b) Within 14 days of receipt of a complete application, the department shall provide written notification to the applicant of the acceptance or rejection of the PBN.
(c) The department shall accept a PBN application if the following requirements are met:
- (1) The project meets the eligibility requirements in Env-Wq 1512.03;
- (2) The information requested in Env-Wq 1512.04 has been submitted; and
- (3) The department does not have evidence that work has already been done for which a permit is required but was not obtained.
- (d) If the department determines that any of the criteria in (c), above, is not met, the department shall reject the PBN application and apply the fee paid as a credit toward the standard application filing fee for the project.
- (e) If the PBN application is rejected, the notice shall specify the reason(s) for the rejection.
(f) If a PBN application is accepted:
(1) The plans and stormwater management report and documentation contained in the permit application submitted to the department with that notification shall be considered part of the
PBN;
- (2) The work shall be done in compliance with the criteria listed in Env-Wq 1503.19(a) thorough (j); and
- (3) The requirements in Env-Wq 1500 shall apply to the PBN.
Source. #14472, eff 1-19-26, EXPIRES: 1-19-36