- (a) The permit holder or permit holder’s agent shall notify the department in writing prior to commencing any work under the permit.
(b) Upon completion of construction, the permit holder or permit holder’s agent shall submit to the department the following:
- (1) A written notice signed as required by Env-Wq 1503.10 by the permit holder and the qualified engineer, if the approved plans and specifications were prepared by a qualified engineer, certifying that the project was constructed in accordance with the approved plans;
- (2) The date the project was completed;
- (3) If insignificant deviations from the approved plans were made, submit as-built drawings and a description of all deviations from the approved plans that have been stamped by a qualified engineer if the approved plans were stamped by a qualified engineer; and
(4) If any underground detention systems, infiltration systems, or filtering systems were installed, the following for each such system:
- a. Representative photographs of the system after completion but prior to being backfilled; and
- b. A letter signed by a qualified engineer stating that the individual observed the system prior to the system being backfilled, and that in the engineer’s professional opinion, the system conforms to the approved plans and specifications.
Source. #9343, eff 1-1-09; ss by #9817-A, eff 12-1-10; ss by #12342, eff 8-15-17; ss by #14472, eff 1-19-26, EXPIRES: 1-19-36 (formerly Env-Wq 1503.21)