- (a) Subject to (b), below, as specified in RSA 483-B:5-b, I(a), no person shall commence construction, excavation, or filling activities within the protected shoreland without obtaining a permit from the department to ensure compliance with RSA 483-B, subject to the exceptions specified in RSA 483-B or established in Env-Wq 1406.03 or Env-Wq 1406.04 pursuant to RSA 483-B:17, X.
- (b) A person may commence construction, excavation, or filling activities within the protected shoreland pursuant to a permit by notification upon receipt of acceptance of the PBN filing by the department or as otherwise provided in RSA 483-B:5-b, V(d).
Source. (See Revision Notes #1 and #2 at chapter heading for Env-Wq 1400) #12062 eff 12-17-16