- (a) All test pit data shall be logged by or under the supervision of a permitted designer.
- (b) Data for each test pit dug shall be submitted in writing to the department and shall bear the stamp of the permitted designer.
- (c) Subject to (d), below, test pit data observed and logged by a permitted designer, other than the permitted designer submitting the application, may be used provided the permitted designer submitting the application assumes responsibility for the accuracy of the data in the test pit log.
- (d) The test pit data submitted with an application by a permitted designer shall be recorded in a test pit log, or the applicant shall obtain written authorization from the original permitted designer to use test pit data that had previously been logged for the property.
Source. (See Revision Notes #1 and #2 at chapter heading for Env-Wq 1000) #11184, eff 10-1-16; ss by #14486, eff 2-1-26, EXPIRES: 2-1-36