(a) There shall be 2 basic types of work plans, as follows:
- (1) Project-specific work plans, developed for the performance of work involving a discrete project at a discrete time and place; and
- (2) Generic work plans, developed for the performance of recurrent types of work that will be undertaken at indeterminate times and places, including but not limited to utility/transportation projects.
- (b) A project-specific work plan shall be used to establish the work procedures to be used by persons disturbing asbestos at a specific asbestos disposal site during a project that is planned in advance of the work actually taking place.
- (c) A generic work plan shall be used to establish the work procedures to be used by persons disturbing asbestos during projects that are routinely undertaken by the responsible party at various locations and at various times not specifically known at the time the plan is prepared.
Source. #7647, eff 2-16-02 (See Revision Note at chapter heading for Env-Sw 2100) (formerly Env-Wm 3906.03); ss by #9645, eff 2-16-10; ss by #12605, eff 9-1-18