(a) To reduce the potential for asbestos fibers to be released to the environment by persons and equipment leaving a major or minor project site, site work zones shall be established and delineated to:
- (1) Separate clean operations from contaminated operations; and
- (2) Control the flow of personnel and equipment between such operations.
- (b) The site work zones required to comply with (a), above, shall be established and maintained in accordance with the provisions for site control provided in Chapter 9 of the Occupational Safety and Health Guidance Manual for Hazardous Waste Site Activities, NIOSH publication No. 85-115, available as noted in Appendix B.
Source. #7647, eff 2-16-02 (See Revision Note at chapter heading for Env-Sw 2100) (formerly Env-Wm 3905.09); ss by #9645, eff 2-16-10; ss by #12605, eff 9-1-18