A standard permit facility, emergency permit facility not exempt pursuant to Env-Sw 313.02(b), and research and development permit facility not exempt pursuant to Env-Sw 312.02(b), shall comply with the following requirements:
(a) The permittee shall designate a project engineer to:
- (1) Administer the technical aspects of the construction contract; and
- (2) Provide technical coordination of the design, permitting, and construction issues;
(b) The project engineer shall:
- (1) Be a qualified professional engineer;
- (2) Administer all construction contracts related to technical issues;
- (3) Approve all construction contract change orders related to technical aspects of the construction;
- (4) Monitor all inspections and testing;
- (5) Provide statements and reports bearing the signature and seal of a qualified engineer as required by Env-Sw 1104.04, Env-Sw 1104.05, Env-Sw 1104.07, and Env-Sw 1105.02;
- (6) Maintain facility construction records during the construction period;
- (7) Monitor all construction activities to ensure compliance with the permit, specifically including the approved design plans and specifications;
- (8) Monitor the scheduling of all construction activities;
- (9) Generate the written status report required by Env-Sw 1104.07 at the end of each 2 week period; and
- (10) Assure compliance with a quality assurance/quality control plan pursuant to Env-Sw 805.16 if applicable;
- (c) Either the project engineer or a qualified resident engineer shall be on site at all times when construction activities are performed;
(d) The qualified resident engineer required by (c) above shall be a qualified professional engineer or shall:
- (1) Work under the supervision of a qualified professional engineer;
- (2) Be experienced in and knowledgeable about the work they will be overseeing; and
- (3) Report directly to the project engineer; and
(e) The requirements of (a) through (d) above shall not apply if:
- (1) The permittee has demonstrated in the permit application, or the application for a permit modification for construction plan approval, that the nature and scope of the proposed construction activity(s) does not require professional engineering oversight to assure protection of the environment, public health and safety, and to meet other requirements of law; and
- (2) The exclusion is approved as a condition of the permit or permit modification.
Source. #6619-B, eff 10-29-97; (See Revision Note at chapter heading for Env-Sw 1100); ss by #8459, eff 10-28-05 (formerly Env-Wm 2804.06); ss by #10598, eff 7-1-14; ss by #14108, eff 11-13-24, EXPIRES: 11-13-34