- (a) The responsible party shall perform an initial site characterization if requested by the department pursuant to Env-Or 605.07.
- (b) The responsible party shall submit a report of the initial site characterization required in (a), above, to the department within 60 days of a department request for an initial site characterization.
(c) The initial site characterization shall:
- (1) Determine the source, location, and estimated quantity of the known or potential discharge and any response actions taken;
- (2) Determine the nature and extent of contamination encountered; and
- (3) Identify nearby receptors and potential receptors.
Source. (See Revision Note at chapter heading for Env-Or 600) #8812, eff 2-1-07; ss by #10831, eff 6-1-15; ss by #14419, eff 11-4-25, EXPIRES: 11-4-35