- (a) The owner shall not backfill or place into service, and shall not authorize any other person to backfill or place into service, a new or substantially modified UST system until after the department has performed an inspection and determined that the system as installed conforms to the approved plans and specifications or as-built record drawings, as applicable, as specified in this section.
- (b) To request authorization to place a new or substantially modified UST into service, the owner shall contact the department to arrange for an inspection of the new or substantially modified system at least 5 department business days prior to the estimated date the tank top or piping, or both, will be backfilled.
- (c) At least 8 department working hours prior to an inspection by the department, the owner shall submit to the department a letter prepared and stamped by a New Hampshire licensed professional engineer (NH PE), stating that the installed UST system has been inspected by a NH PE to verify that the system was constructed in accordance with the department’s approved plans and specifications.
- (d) If the NH PE’s inspection reveals any discrepancies between the system as installed and the approved plans and specifications, the owner shall submit to the department as-built record drawings prepared and stamped by a NH PE prior to the backfill inspection conducted by the department.
(e) If the department determines, as a result of its inspection, that the system as installed does not conform to the approved plans and specifications, the owner shall:
- (1) Submit as-built record drawings prepared and stamped by a NH PE to the department within 30 days of the department’s inspection; and
- (2) Notify the department to arrange a follow-up inspection.
(f) After the department determines that the system as installed conforms to the approved plans and specifications or as-built plans, as applicable, the system may be backfilled but shall not be placed into service until the owner has submitted:
- (1) All information required for registration specified in Env-Or 404.01(a) and (b);
- (2) A stage I/stage II notification and system test report if and as required by Env-Or 500; and
- (3) A statement identifying the class A and class B operators, as required by RSA 146-C:17.
Source. (See Revision Note #1 at chapter heading for Env-Or 400) #10393, eff 9-1-18; ss by #12643, eff 10-10-18 (See Revision Note #2 at chapter heading for Env-Or 400)