(a) As specified in RSA 146-C:7, I, prior to commencing construction or installation of a new facility or making one or more substantial modifications at an existing facility, including any changes to a cathodic protection system, the owner shall:
- (1) As required by RSA 146-C:7, I, submit plans and specifications to the department; and
- (2) Provide the information required by Env-Or 407.02 together with the fee, if any, required by RSA 146-C:7, I-a.
- (b) The approval of the plans by an engineer licensed to practice in New Hampshire that is required by RSA 146-C:7, I shall be demonstrated by the engineer signing and affixing his or her stamp to the plans.
- (c) Subject to (d), below, construction shall not commence until the sooner of 90 days after submitting a complete application or the department issues an approval.
- (d) If the department issues a denial within 90 days, the facility shall not be constructed.
- (e) The owner shall sign and date the application.
(f) The signature shall constitute certification that:
- (1) The information provided is true, complete, and not misleading to the knowledge and belief of the signer;
- (2) The signer understands that any permit issued based on false, incomplete, or misleading information shall be subject to revocation; and
- (3) The signer understands that he or she is subject to the penalties for falsification in official matters currently specified in RSA 641.
Source. (See Revision Note #1 at chapter heading for Env-Or 400) #10393, eff 9-1-18; ss by #12643, eff 10-10-18 (See Revision Note #2 at chapter heading for Env-Or 400)