(a) The owner of an AST system included in Env-Or 309.01(c), temporary construction AST system, shall:
- (1) Register the temporary construction AST system as specified in Env-Or 304.01; and
- (2) Include the contract start and completion dates in the registration information.
(b) A temporary construction AST system shall:
- (1) Be marked as specified in Env-Or 305.03;
- (2) Have secondary containment as specified in Env-Or 305.07;
- (3) Be equipped with a gauge as specified in Env-Or 305.11(a); and
- (4) Be equipped with either a high level warning alarm as specified in Env-Or 305.11(b) or a mechanically operated automatic fill shut-off valve as specified in Env-Or 305.08(h)(3).
Source. (See Revision Note at chapter heading for Env-Or 300) #10487, eff 2-7-14; ss by #14094, eff 10-4-24