- (a) At least 45 days prior to commencing construction or installation of a new or replacement AST system having an oil storage capacity of more than 660 gallons that is subject to these rules, the owner of the existing or proposed facility shall submit the application materials specified in (c), below, to the department.
- (b) At least 45 days prior to commencing construction or installation of any new or replacement underground or over-water piping systems as part of an AST system having an oil storage capacity of more than 660 gallons, the owner of the existing or proposed facility shall submit the application materials specified in (c), below to the department.
(c) The application materials required to be submitted by (a) and (b), above, shall be:
- (1) A completed application form as specified in Env-Or 307.02(a), signed as specified in Env-Or 307.02(b);
- (2) Complete plans and specifications as specified in Env-Or 307.03 that have been prepared, approved, and stamped on each page by a New Hampshire licensed professional engineer; and
- (3) A spill prevention control and countermeasure plan as specified in Env-Or 306.02.
Source. (See Revision Note at chapter heading for Env-Or 300) #10487, eff 2-7-14; ss by #14094, eff 10-4-24