- (a) After the application is deemed complete in accordance with Env-Hw 304.15, the commissioner or designee shall assign a staff engineer to conduct a complete technical review of the application, including a determination as to whether the proposed facility could be sited or operated, or a proposed activity could be conducted, such that human health, safety, and the environment will be protected.
- (b) The engineer assigned pursuant to (a), above, shall evaluate all information submitted with the application, all facility requirements, and all information submitted during the public comment period and public hearings conducted in accordance with Env-Hw 304.21.
Source. (See Revision Note at chapter heading for Env-Hw 300) #9362, eff 1-28-09; ss by #12345, eff 8-14-17 (formerly Env-Hw 304.18); ss by #13406, eff 7-23-22