- (a) Upon receiving an application for a new listing, the department shall review it to determine whether it contains everything required by Env-C 503.01.
- (b) If the submission does not contain everything required by Env-C 503.01, the department shall notify the applicant within 15 calendar days of what is missing.
- (c) The department shall review each application for a new listing within 30 calendar days of receipt of a complete application.
(d) The department shall approve the application for a new listing if, based on the information provided by the applicant or otherwise available to the department:
- (1) The applicant and its qualifying professional engineers demonstrate professional competence in each category for which prequalification is sought; and
- (2) The department is not aware of any basis for debarment as specified in Env-C 503.07.
- (e) If the department denies the application, the written notice shall specify the reason(s) for the denial.
Source. (See Revision Note at chapter heading for Env-C 500) #10644, eff 7-22-14; ss by #14060, eff 8-21-24 (formerly Env-C 503.04)