- (a) This chapter shall apply to affected sources as defined in RSA 125-O:2, I, namely “existing fossil fuel burning steam power plant units in this state, specifically Merrimack Units 1 and 2 in Bow; Schiller Units 4, 5, and 6 in Portsmouth; and Newington Unit 1 in Newington, excluding any of these units that may be repowered.”
- (b) Because Schiller Unit 5 commenced operation after repowering on October 20, 2006, that unit shall not be subject to this chapter.
Source. #10002, eff 10-1-11; ss by #12995, eff 2-25-20