(a) The owner or operator shall submit a revised notification to the department, as specified in (b) through (f) below, if any of the following occurs during an asbestos abatement:
- (1) The asbestos abatement entity assigned to the asbestos abatement changes;
- (2) The type of asbestos affected changes;
- (3) The completion date of the asbestos abatement changes;
- (4) An unscheduled change, of more than one day, to the dates or hours of operation occurs;
- (5) The amount of asbestos affected changes by 20% or more;
- (6) The amount of asbestos increases resulting in an increase in the notification fee required under Env-A 1806.08(b);
- (7) The start date of the asbestos abatement changes; or
- (8) Additional locations within a facility where asbestos is to be removed are added to the asbestos abatement.
(b) The owner or operator shall submit a revised notification for changes specified in (a)(1) through (a)(6) by:
- (1) Notifying the department within 24 hours via telephone as specified in Env-A 1801.03(b) or electronic means;
- (2) Completing the revised notification form as specified in Env-A 1806.03(a);
- (3) Submitting the form and revised notification fee, as specified in Env-A 1806.08, to the department by mail, hand delivery, or electronic means; and
- (4) Ensuring that the form and fee are postmarked, delivered to the department, or received by the department within 48 hours of notifying the department pursuant to (b)(1) above.
- (c) For changes specified in (a)(6), above, the owner or operator shall also submit the notification fee required in Env-A 1806.08(b)(1) or (b)(2), as applicable, minus any amount already paid, pursuant to Env-A 1806.08(b)(2) or (b)(3), as applicable.
(d) If the revised start date of the asbestos abatement, pursuant to (a)(7) above, is earlier than the original start date of the asbestos abatement, the owner or operator shall:
- (1) Complete the revised notification form as specified in Env-A 1806.03(a), above;
- (2) Submit the revised notification form and notification fee, as specified in Env-A 1806.08, to the department by mail, hand delivery, or electronic means; and
- (3) Ensure that the revised notification form is postmarked, delivered to the department, or received by the department at least 10 working days before the revised start date of the asbestos abatement.
(e) If the revised start date of the asbestos abatement, pursuant to (a)(7) above, is later than the original start date of the asbestos abatement, the owner or operator shall:
- (1) Notify the department by telephone or electronic means at least 24 hours before the original start date; and
- (2) Submit the revised notification form, as specified in Env-A 1806.03(a), and the revised notification fee, as specified in Env-A 1806.08, to the department by mail, hand delivery, or electronic means such that the form and fee are postmarked, delivered to the department, or received by the department within 24 hours of notifying the department, pursuant to (1) above.
(f) At least 10 days before work begins in a new location, as specified in (a)(8) above, the owner or operator shall mail, hand-deliver, or submit by electronic means, the following to the department:
- (1) The revised notification form as specified in Env-A 1806.03(a) and revised notification fee, as specified in Env-A 1806.08; and
- (2) For a project at a school subject to AHERA, a revised design plan showing that the new location has been properly inspected for asbestos, in accordance with Env-A 1804.01.
- (g) For asbestos abatement, an initial notification and any subsequent revised notifications shall expire on the completion date specified in the notification, unless a revision is received by the department as specified in (b) through (f) above, as applicable.
- (h) For any revisions to be made to a notification other than those listed in (a), above, the owner or operator shall submit, by mail, hand delivery, or electronic means, a revised notification form, as specified in Env-A 1806.03(a), and revised notification fee as specified in Env-A 1806.08, to the department within 2 business days of discovering the need to revise the form or of being requested by the department to revise the form.
(i) To cancel a previously submitted notification which has not expired pursuant to (g), above, the owner or operator shall submit, by email or electronic means, a request to cancel the notification to the department including:
- (1) The facility address; and
- (2) The start and completion dates of the asbestos abatement.
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24; ss by #14467, eff 1-1-26, EXPIRES: 1-1-36