(a) In any notification specified in Env-A 1806.02(a)(1), the owner or operator shall:
- (1) Complete and submit the “Asbestos Abatement Notification”, form NHDES-A-01-016, dated August 20, 2024, available at https://onlineforms.nh.gov/?FormTag=NHDES-A-01-016 or via the department’s website at www.des.nh.gov; and
(2) Provide the following information:
- a. An indication of whether the notice is a new or revised notification;
- b. The amount of the fee included with the form;
- c. An indication of whether the project is an emergency asbestos abatement;
d. For emergency asbestos abatement, the following:
- 1. Date and hour that the emergency occurred;
- 2. A description of the sudden, unexpected event; and,
- 3. An explanation of why immediate action is needed to address a public health or safety hazard or to avoid imposing an unreasonable economic hardship;
- e. Name, physical address, county, and floor or room number, if applicable, of the facility being demolished or renovated;
- f. Description of the facility or affected part of the facility including the size in square feet, number of floors, year constructed, current use, and prior use of the facility;
- g. Date of the inspection, name of the person who conducted the inspection, and certification number of the asbestos inspector;
- h. Type of inspection, including visual and analytical methods, employed to detect the presence of ACM;
- i. If analytical methods were used, describe those;
- j. List the types of asbestos and location in the facility;
- k. An estimate of the approximate amount of RACM to be removed from the facility in terms of length of pipe in linear feet, surface area in square feet on other facility components, or volume in cubic feet if off the facility components;
l. Scheduled start and completion dates of asbestos removal work or any other activity, such as site preparation that would break up, dislodge, or similarly disturb asbestos material in a demolition or renovation;
m Weekly work schedule including days of the week and time of day of work;
- n. Description of planned asbestos abatement work to be performed and method(s) to be employed, including demolition or renovation techniques to be used and description of affected facility components;
- o. Description of work practices and engineering controls to be used, including asbestos removal and waste-handling emission control procedures;
- p. Name and mailing address of the facility owner and asbestos abatement entity;
- q. Contact information, including name, email address, telephone type, and telephone number for the facility owner or designee;
- r. Contact information, including name, email address, telephone type, and telephone number for the asbestos abatement entity;
- s. Description of procedures to be followed if unexpected RACM is found or Category II nonfriable ACM becomes crumbled, pulverized, or reduced to powder;
- t. A certification that at least one person certified as required by Env-A 1816.02 relative to asbestos abatement supervisor certification requirements shall, at all times, supervise the asbestos abatement described by this notification;
- u. License number of the asbestos abatement entity; and
v. A certification that:
- 1. The owner or operator has read and understands the New Hampshire asbestos management and control rules, Env-A 1800;
- 2. The notification is prepared in conformity with Env-A 1800; and
- 3. All information contained in the notification, including any supplements attached, is true, complete, and not misleading to the best of the owner or operator’s knowledge and belief.
- (b) For asbestos abatement at a school subject to AHERA, attach a copy of the design plan to the notification submitted, pursuant to (a), above.
(c) The initial notification required by Env-A 1806.02 and the notification fee, as required by Env-A 1806.08, shall:
- (1) Contain the information specified in (a) and (b), above, as applicable;
- (2) Be submitted to the department by mail, hand delivery, or electronic means; and
- (3) Be submitted such that the notice and fee are postmarked or received by the department at least 10 working days before any asbestos abatement begins.
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24, EXPIRES: 11-1-34