(a) Before completing asbestos abatement or disposing of ACM, the homeowner shall package ACM in accordance with Env-Sw 901.06, and as follows:
(1) For all loose ACM, take the following actions to prevent the release of fibers:
- a. Adequately wet the ACM with amended water;
- b. Place the ACM into leak-tight containers or double impermeable bags of at least 6 mil thickness each; and
- c. Seal the containers or bags with tape, as applicable;
- (2) Wrap large components or structural members that were removed intact in 2 leak-tight layers of 6 mil sheeting and seal the sheeting with tape; and
- (3) Line the containers, into which bulk unwrapped asbestos waste is placed, with at least 20 mil of sheeting.
(b) The homeowner shall label ACM, in accordance with Env-Sw 901.06, and as follows:
(1) Label the containers or wrapped materials using warning labels, as follows:
- a. Printed in letters of sufficient size and contrast so as to be readily visible and legible; and
- b. As specified in 29 CFR 1910.1001(j)(5) or 1926.1101(k)(8); and
- (2) For asbestos-containing waste material to be delivered to a permitted disposal facility, label containers or wrapped materials with the name of the homeowner and the location at which the waste was generated.
Source. (See Revision Note #1, Revision Note #2, and Revision Note #3 at chapter heading for Env-A 1800) #14104, eff 11-1-24, EXPIRES: 11-1-34