- (a) Each applicant shall complete and submit an application.
(b) Each applicant shall include with each application for review of a residential building for compliance with the energy code, the following:
- (1) A completed, signed electronic copy of the application available on the BCRB website; and
(2) A certification by the applicant, as follows:
“I hereby certify that all the information contained in this application is true and correct, and construction shall comply in all respects with the New Hampshire Building Code.”
- (c) Applicants may submit applications to the department by electronic mail to energycodes@energy.nh.gov.
- (d) For purposes of RSA 155-A:10-a, any application submitted shall not be deemed complete until all components of the application as required at En 1803.01(b) have been received by the department. The failure of an applicant to respond to an inquiry by the department within 10 business days of such inquiry shall render the application rejected.
- (e) If an applicant makes a substantive revision to an application, including but not limited to a revision to a design specification, after the application has been submitted to the department, the applicant shall date and initial in ink or electronically the revision made to the application.
- (f) The date of the submitted revision, as described in En 1803.01(e) above, shall constitute a new receipt date for the application.
- (g) An owner of a residential building for which plans and specifications have been approved by an architect or engineer pursuant to RSA 155-A shall submit them to the department as prescribed by the BCRB.
Source. #14381, eff 9-22-25, EXPIRES: 9-22-35