- (a) Notwithstanding En 1503.01, an application shall not be required with respect to limited maintenance or temporary construction provided that notification is given to the department within a reasonable time not to exceed 7 days after the inception of such activities and provided further notification also is given to the department within 7 days of completion.
- (b) Notwithstanding En 1503.01, an application shall not be submitted in advance of emergency construction or modification provided that notice is given to the department within a reasonable time not to exceed 7 days after the inception of work and provided further that an application is filed within 90 days after completion.
Source. #13939, eff 4-26-24