N.D. Admin. Code § 33.1-24-01-09
In accordance with the standards and criteria in sections 33.1-24-01-10 and 33.1-24-01-17 and the procedures in section 33.1-24-01-12, the department may determine on a case-by-case basis the following recycled materials are not solid wastes:
1. Materials that are accumulated speculatively without sufficient amounts being recycled (as defined in subdivision h of subsection 3 of section 33.1-24-02-01);
2. Materials that are reclaimed and then reused within the original production process in which they were generated;
3. Materials that have been reclaimed but must be reclaimed further before the materials are completely recovered;
4. Hazardous secondary materials that are reclaimed in a continuous industrial process;
5. Hazardous secondary materials that are indistinguishable in all relevant aspects from a product or intermediate.
History: Effective January 1, 2019; amended effective July 1, 2020.
General Authority: NDCC 23.1-04-03; S.L. 2017, ch. 199, § 1