Proposed temporary structures shall meet each of the following specific conditions to be eligible for authorization by the general permit:
- (1) All aspects of the structure shall be removed and the site returned to pre‑project conditions at the expiration of this general permit.
- (2) There shall be no work within any productive shellfish beds without authorization from the Division of Marine Fisheries.
- (3) The proposed structure shall not involve the disturbance of any marsh, submerged aquatic vegetation, or other wetlands including excavation or filling of these areas.
- (4) The proposed activity shall not disrupt navigation and transportation channels and shall be marked to prevent being a hazard to navigation.
- (5) The proposed structure shall not impede public access or other public trust uses.
- (6) The proposed structure shall not be habitable.
- (7) There shall be no disturbance of existing dunes.
- (8) Temporary structures authorized by this permit shall not individually or cumulatively exceed 100 square meters in size.
- (9) Structures shall not be constructed in a designated Primary Nursery Area without approval from the Division of Marine Fisheries or the Wildlife Resources Commission.
History Note: Authority G.S. 113‑229(c1); 113A‑107(a)(b); 113A‑113(b); 113A‑118.1;
Eff. March 1, 1989;
Amended Eff. April 1, 2020; May 1, 1990;
Readopted Eff. July 1, 2022.