(a) An "administrative permit amendment" means a permit revision that:
- (1) corrects typographical errors;
- (2) identifies a change in the name, address, or telephone number of any individual identified in the permit or provides a similar minor administrative change at the facility;
- (3) requires more frequent monitoring or reporting by the permittee;
- (4) changes test dates or construction dates, provided that no applicable requirements are violated by the change in test dates or construction dates; or
- (5) changes the permit number without changing any portion of the permit that would not otherwise qualify as an administrative amendment.
(b) In making administrative permit amendments, the Director:
- (1) shall take final action on a request for an administrative permit amendment within 60 days after receiving such a request; and
- (2) shall make administrative amendments using the criteria in Paragraph (a) without providing notice to the public.
- (c) The permittee may implement the changes addressed in the request for an administrative amendment immediately upon submittal of the request.
History Note: Authority G.S. 143‑215.3(a)(1); 143‑215.108;
Eff. April 1, 2001;
Readopted Eff. April 1, 2018.