Reports shall be submitted by the borrower as follows:
(1) progress reports shall be submitted quarterly to the State Energy Office during the period of implementation or while installation is in progress and shall include a description of:
(2) a final report certified by the Technical Analyst shall be submitted to the State Energy Office upon completion of the project. The report shall include a description of: