04 NCAC 11 R08-71
(b) Definitions.
(c) Initial CPRE Program Filings and Program Guidelines
(1) Each electric public utility shall develop and seek Commission approval of guidelines for the implementation of its CPRE Program and to inform market participants regarding the terms and conditions of, and process for participating in, the CPRE Program. The electric public utility shall file its initial CPRE Program guidelines at the time it initially proposes a CPRE Program for Commission approval. The CPRE Program guidelines should, at minimum, include the following:
(d) Selection and Role of Independent Administrator.
(5) The Independent Administrator's duties shall include:
(e) Communications Between CPRE Market Participants.
(4) There shall be no communications, either directly or indirectly, between the Proposal Team and Evaluation Team during the CPRE RFP Solicitation regarding any aspect of the CPRE RFP Solicitation process, except (i) necessary communications as may be made through the Independent
Administrator and (ii) negotiations between the Proposal Team and the Evaluation Team for a final power purchase agreement after the Proposal Team has been selected by the electric public utility as a winning proposal. The Evaluation Team will have no direct or indirect contact or communications with the Proposal Team or any other participant, except through the Independent Administrator as described further herein, until such time as a winning proposal or proposals are selected by the electric public utility and negotiations for a final power purchase agreement(s) have begun.
(f) CPRE RFP Solicitation Structure and Process.
(1) Identification of Market Participants; Design of CPRE RFP Solicitation.
(2) Issuance of CPRE RFP Solicitation.
(3) Evaluation and Selection of Proposals. The evaluation and selection of proposals received in response to a CPRE RFP Solicitation shall proceed in two steps as set forth in this subdivision, and shall be subject to the Commission's oversight as provided in G.S. 62-110.8 and this rule.
(g) CPRE Program Plan.
(2) Each year, beginning in 2018, each electric public utility shall file with the Commission an updated CPRE Program plan covering the remainder of the CPRE Program Procurement Period. At a minimum, the plan shall include the following information:
(h) CPRE Program Compliance Report.
(2) Beginning in 2019, and each year thereafter, each electric public utility shall file with the Commission a report describing the electric public utility's competitive procurement of renewable energy resources under its CPRE Program and ongoing actions to comply with the requirements of G.S. 62‑110.8 during the previous calendar year, which shall be the "reporting year." The report shall include the following information, including supporting documentation:
(i) Compliance with CPRE Program Requirements.
(j) Cost or authorized revenue recovery.
(k) Expedited review and approval of Certificate of Public Convenience and Necessity for renewable energy facilities owned by an electric public utility and procured under the CPRE Program.
(1) Scope of Section.
(2) The Application. The application shall be comprised of the following exhibits:
(i) Exhibit 1 shall contain:
1. The full and correct name, business address, business telephone number, and electronic mailing address of the electric public utility;
2. A statement describing the electric public utility's corporate structure and affiliation with any other electric public utility, if any; and
3. The ownership of the facility site and, if the owner is other than the applicant, the applicant's interest in the facility site.
(ii) Exhibit 2 shall contain the following site information:
1. A color map or aerial photo showing the location of the generating facility site in relation to local highways, streets, rivers, streams, and other generally known local landmarks, with the proposed location of major equipment indicated on the map or photo, including: the generator, fuel handling equipment, plant distribution system, startup equipment, site boundary, planned and existing pipelines, planned and existing roads, planned and existing water supplies, and planned and existing electric facilities. A U.S. Geological Survey map or an aerial photo map prepared via the State's geographic information system is preferred;
2. The E911 street address, county in which the proposed facility would be located, and GPS coordinates of the approximate center of the proposed facility site to the nearest second or one thousandth of a degree; and
3. Whether the electric public utility is the site owner, and, if not, providing the full and correct name of the site owner and the electric public utility's interest in the site.
(iii) Exhibit 3 shall include:
1. The nature of the renewable energy facility, including the type and source of its power or fuel;
2. A description of the buildings, structures and equipment comprising the renewable energy facility and the manner of its operation;
3. The gross and net projected maximum dependable capacity of the renewable energy facility as well as the renewable energy facility's nameplate capacity, expressed as megawatts (alternating current);
4. The projected date on which the renewable energy facility will come on line;
5. The service life of the project;
6. The projected annual hourly production profile for the first full year of operation of the renewable energy facility in kilowatt-hours, including an explanation of potential factors influencing the shape of the production profile, including the following, if applicable: fixed tilt or tracking panel arrays, inverter loading ratio, over-paneling, clipped energy, or inverter AC output power limits;
7. The projected annual production of renewable energy certificates that is eligible for compliance with the State's renewable energy and energy efficiency portfolio standard.
(iv) Exhibit 3 shall include:
1. A complete list of all federal and state licenses, permits and exemptions required for construction and operation of the renewable energy facility and a statement of whether each has been obtained or applied for; and
2. A copy of those that have been obtained should be filed with the application; a copy of those that have not been obtained at the time of the application should be filed with the Commission as soon as they are obtained.
(vi) Exhibit 5 shall contain the following resource planning information:
1. The utility's most recent biennial report and the most recent annual report filed pursuant to Rule R8-60, plus any proposals by the utility to update said reports;
2. The extent to which the proposed facility would conform to the utility's most recent biennial report and the most recent annual report that was filed pursuant to Rule R8-60;
3. A statement of how the facility would contribute to resource and fuel diversity, whether the facility would have dual-fuel capability, and how much fuel would be stored at the site;
4. An explanation of the need for the facility, including information on energy and capacity forecasts; and
5. An explanation of how the proposed facility meets the identified energy and capacity needs, including the anticipated facility capacity factor, heat rate, and service life.
(3) Petition for transfer of certificate of public convenience and necessity. When an electric public utility procures an operating renewable energy facility through a CPRE RFP Solicitation with intent to own and operate the facility and the renewable energy facility has been previously issued a certificate of public convenience and necessity, the electric public utility shall petition the Commission to transfer the certificate of public convenience and necessity. A petition requesting that the Commission transfer a certificate of public convenience and necessity shall include the following:
(5) Procedure for expedited review of applications for a certificate of public convenience and necessity. – The Commission will process applications for certificates of public convenience and necessity filed pursuant to this section as follows:
(i) The electric public utility shall file with the Commission its preliminary plans at least 30 days before filing an application for a certificate of public convenience and necessity. The preliminary plans shall include the following:
1. Exhibit 1 shall contain the following site information:
a. A color map or aerial photo (a U.S. Geological Survey map or an aerial photo map prepared via the State's geographic information system is preferred) showing the proposed site boundary and layout, with all major equipment, including the generator and inverters, planned and existing roads, planned and existing water supplies, and planned and existing electric facilities;
b. The E911 street address, county in which the proposed facility would be located, and GPS coordinates of the approximate center of the proposed facility site to the nearest second or one thousandth of a degree;
c. The full and correct name of the site owner and, if the owner is other than the applicant, the applicant's interest in the site;
d. A brief general description of practicable transmission line routes emanating from the site, including a color map showing their general location; and
e. The gross, net, and nameplate generating capacity of each unit and the entire facility's total projected dependable capacity in alternating current (AC).
2. Exhibit 2 shall contain a list of all agencies from which approvals will be sought covering various aspects of any generation facility constructed on the site and the title and nature of such approvals; and
3. Exhibit 3 shall include a schedule showing the anticipated beginning dates for construction, testing, and commercial operation of the generating facility.
(6) Procedure for Expedited Transfer of certificate of public convenience and necessity. — The Commission shall process a petition to transfer a certificate of public convenience pursuant to the CPRE Program as follows:
(l) CPRE Program Power Purchase Agreement Requirements
(NCUC Docket No. E-100, Sub 150, 11/06/2017; NCUC Docket No. E-100, Sub 150, 04/09/2018; NCUC Docket No. E-100, Sub 166, 08/31/2020; NCUC Docket No. M-100, Sub 196, 9/18/2023; NCUC Docket No. E-100, Sub 191, 11/21/2023.)