04 NCAC 11 R08-13
(g) Inspections – When metering installations are tested or inspected, instrument transformers and wiring associated with the installation shall be visually inspected for correctness of connections and evidence of damage. Nameplate or stenciled ratios shall be verified against ratios used by the utility for billing. These inspections are not required if performing them cannot be done safely.
(NCUC Docket No. M-100, Sub 5, 7/15/65; NCUC Docket No. E-100, Sub 4, 6/8/66; NCUC Docket No. M-100, Sub 140, 12/03/13; NCUC Docket No. E-100, Sub 153, 11/27/2019.)