(a) Each LDC that has an established Fund shall, on at least an annual basis, file a request for approval of any Project(s) which previously have not been approved and which it proposes to undertake within the next year and for which it proposes to use expansion funds. The request shall include an analysis of each proposed Project. For each proposed Project, the LDC's analysis shall contain the following:
(f) If construction on an approved Project has not begun within one year of the order granting approval, the Commission may require the LDC to show cause why the balance in its Fund allocated to such Project should not be allocated to other approved Projects or otherwise disposed of as ordered by the Commission.
(NCUC Docket No. G-100, Sub 57, 4/9/92.)