In selecting the three firms to be presented to the SBC, the pre‑selection committee should take into consideration such factors as:
- (1) Specialized or appropriate expertise in the type of project.
- (2) Past performance on similar projects.
- (3) Adequate staff and proposed design or consultant team for the project.
- (4) Current workload and State projects awarded.
- (5) Proposed design approach for the project including design team and consultants.
- (6) Recent experience with project costs and schedules.
- (7) Construction administration capabilities.
- (8) Proximity to and familiarity with the area where project is located.
- (9) Record of successfully completed projects without major legal or technical problems.
- (10) Other factors that may be appropriate for the project.
History Note: Authority G.S. 143‑135.25; 143‑135.26;
Eff. January 1, 1988;
Amended Eff. May 1, 1990;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.