- (1) Until the certificate of project completion is issued pursuant to 82-11-183(1) and title to the stored carbon dioxide and geologic storage reservoir is transferred to the state pursuant to 82-11-183(7), the geologic storage operator is liable for the operation and management of the carbon dioxide injection well, the geologic storage reservoir, and the injected or stored carbon dioxide.
- (2) Bond or other surety furnished pursuant to 82-11-123(1)(f) must be adequate to meet the requirements of subsection (1).
- (3) For the purposes of 82-11-183 and this section, "title" includes title to the geologic storage reservoir and the stored carbon dioxide.
History: En. Sec. 3, Ch. 474, L. 2009; amd. Sec. 26, Ch. 123, L. 2013.