- (1) The person, firm, or corporation moving a house, building, derrick, or other structure shall give the person, firm, or corporation owning or controlling the wires, cables, or poles affected by the movement of a structure, at both the person's, firm's, or corporation's principal office and nearest office within the state, not less than 10 days' written notice of the proposed time and place of moving a structure.
- (2) The owner of the wires, cables, or poles shall give the mover a written estimate of the total cost of all work related to cutting or raising the wires or cables or moving the poles, including travel time, at least 3 days prior to the move or within 10 days after receipt of the written notice of the move, whichever time comes sooner.
- (3) The estimate of the total cost required under this section must be developed in accordance with the cost schedule filed as provided in subsection (4).
- (4) A public utility, cable television company, or unregulated telecommunications provider with wires, cables, or poles in Montana shall file with the commission, by April 1 of each year, an application for approval of a cost schedule for labor and equipment for all work related to cutting or raising wires or cables or moving poles. The cost schedule is effective on a temporary basis, subject to a rebate and a surcharge as provided in 69-3-304, 30 days after the filing of a cost schedule and pending a final order of the commission, unless the commission first determines that the cost schedule is above cost.
History: En. Sec. 2, Ch. 55, L. 1929; re-en. Sec. 2711.2, R.C.M. 1935; R.C.M. 1947, 24-137; amd. Sec. 1, Ch. 442, L. 1983; amd. Sec. 1, Ch. 359, L. 2003.