- (1) The EDC shall file standard applications for interconnection requests, standard agreements required by the interconnection rules, a schedule of fees for processing interconnection requests, and a schedule of rates for performing the various studies required by these rules with the commission.
- (2) All agreements, forms, fees, and rates must be filed with and approved by the commission after public notice and opportunity for comment.
- (3) Utilities may not deviate from the standard agreements and fees filed with the commission without commission approval.
- (4) A customer may petition the commission to require the utility to amend its agreements, forms, fees, and rates.
- (5) The commission on its own, may require the utility to amend its agreements, forms, fees, and rates.
Authorizing statute(s): 69-3-103, MCA
Implementing statute(s): 69-3-102, MCA
History: NEW, 2010 MAR p. 1801, Eff. 8/13/10.