(1) The interconnection procedures set forth in this subchapter apply to applicants proposing to install and interconnect a small generator facility to an EDC's system that satisfies the following criteria:
- (a) The small generator facility must be sited on the utility customer's premises;
- (b) The customer installing the small generator facility must be in good standing with the utility;
- (c) The proposed small generator facility's point of interconnection may not be on a transmission line;
- (d) The power produced from the small generator facility must be contained on the EDS and not flow onto the transmission system; and
- (e) The power exported by an interconnection customer can only be sold to the EDC.
Authorizing statute(s): 69-3-103, MCA
Implementing statute(s): 69-3-102, MCA
History: NEW, 2010 MAR p. 1801, Eff. 8/13/10.