- (1) After the effective date of these regulations, tubingless completions or annular injection wells, or wells not equipped to inject through tubing below a packer or other suitable sealing device in the annulus will not be permitted.
- (2) Exceptions to this requirement will be granted for existing wells in a board approved enhanced recovery or pressure maintenance project where the applicant can demonstrate that it is practically or economically not feasible to equip such wells with tubing and packer.
- (3) Mechanical integrity testing and monitoring requirements will be required more frequently and be more stringent for wells permitted as an exception to this rule.
Authorizing statute(s): 82-11-111, MCA
Implementing statute(s): 82-11-111, 82-11-121, 82-11-123, 82-11-124, 82-11-127, 82-11-137, MCA
History: NEW, 1992 MAR p. 2171 and 1996 MAR p. 1308, Eff. 5/10/96.