- (1) The engineering report must include detailed descriptions and design assumptions for the removal, partial removal, or abandonment of the dam.
(2) Plans and specifications must include as a minimum the following:
- (a) a cover sheet indicating the name of the project, name of owner, certification by the engineer and the owner pursuant to ARM 36.14.304 (2b) , designated access to the site, and the location with respect to highways, roads, and streams;
- (b) method of draining the reservoir during removal and statement of the sequence of operations;
- (c) method of disposal or stabilization of the sediment;
- (d) disposition of the dam materials;
- (e) description of the reclamation actions to be applied to the dam and impoundment area; and
- (f) means for removal of the dam to prevent future impoundment.
Authorizing statute(s): Sec. 85-15-110, MCA
Implementing statute(s): Sec. 85-15-210, MCA