(1) For this SMA:
- (a) The entire SMA must be lopped such that 90% of all slash three inches or less in diameter is reduced to a height of 24 inches or less above the ground.
- (b) Slash piles at the landing area must be treated in compliance with ARM 36.11.223 or this rule, whichever is applicable.
- (c) The department may approve other methods when such methods would maintain public and firefighter safety.
Authorizing statute(s): 76-13-403, MCA
Implementing statute(s): 76-13-403, 76-13-406, 76-13-407, 76-13-408 and 76-13-410, MCA
History: NEW, 2000 MAR p. 2526, Eff. 9/22/00.