Admin. R. Mont. 17.74.406
(2) Table 1 - Permit Fees:
| Permit Fee | Amount of Permit Fee |
| Asbestos project permit | Fees are calculated by AUMs using Table 2 |
| Annual asbestos project permit, authorizes the removal or disturbance of up to 25,000 AUMs during the annual project permit period | $4,000 |
| Annual asbestos project permit revision authorizes cumulative removal or disturbance that exceeds 25,000 AUMs | $700 plus AUM fees in Table 2 for regulated asbestos-containing material that exceeds 25,000 AUMs |
| Demolition notice | $100 |
| Demolition revisions | $100 |
| Project permit revision | $100 plus the additional AUM fees (If there is a change in the AUM range, a person would pay the difference between the two ranges in Table 2) |
| Emergency renovation notification (ARM 17.74.352) | $300 plus AUM fees in Table 2 |
| Submission of alternate work practice request (ARM 17.74.353) | $100 |
| Voluntary registration for a non-regulated asbestos abatement project (as in (4)) | $100 plus AUM fees in Table 2 if the project becomes regulated and exceeds 100 AUMs |
| Ordered demolition | $300 |
| Transportation and disposal permit | $100 |
(3) Table 2 - AUM Fees:
| AUM Range | AUM Fee Amount |
| up to 100 | $100 |
| 101 to 300 | $150 |
| 301 to 500 | $200 |
| 501 to 750 | $300 |
| 751 to 1,500 | $600 |
| 1,501 to 3,000 | $1,000 |
| 3,001 to 5,000 | $2,000 |
| 5,001 to 10,000 | $3,000 |
| 10,001 to 25,000 | $4,000 |
| 25,001 to 50,000 | $6,000 |
| 50,001 to 100,000 | $8,000 |
| 100,001 or more | $16,000 |
Authorizing statute(s): 75-2-503, MCA
Implementing statute(s): 75-2-503, 75-2-504, MCA
History: NEW, 2020 MAR p. 1325, Eff. 7/1/20.