LOCAL GOVERMENTS AND RURAL WATER SYSTEMS IMPROVEMENTS BOARD
3.1.1
All drinking water system projects funded by the DWSIRLF must comply with the
3.2.1
Preplanning Guidance and Conference
3.2.2
Project Information and Planning Documentation
3.2.3
Environmental Review Process
3.2.4
Submittal of Project Information (Part 1
3.2.5
Determination of Planning Documentation Sufficiency
3.3.1
Pre-application Guidance and Conference
3.3.2
Contents of Applications
3.3.3
Submittal of application
3.4.1
Upon determination by the Department that (a)all application and documentation
3.4.2
Upon receipt of the DWSIRLF loan offer, the loan recipient must completely execute
3.5.1
Predesign Guidance and Conference
3.5.2
Plans, Specifications and Contract Documents
3.6.1
Within the timeframe established in the loan agreement, the loan recipient must
3.6.2
Upon receipt of construction bids, the loan recipient must then submit a) the
3.6.3
Upon receipt of the items listed in Rule 3.6.2 above, the Department will review them
3.6.4
Amended Loan Offer
3.7.1
Construction
3.7.2
Observation During Construction
3.7.2.3
The contractor, registered engineer, and the loan recipient must furnish the
3.7.3
Observation of Materials and Equipment
3.7.4
Construction Deficiencies
3.7.5
Change Orders
3.7.6
Contractor Bankruptcy or Default
3.7.7
Construction Phase Submittals, Approvals, and Actions
3.8.1
Following final payment of DWSIRLF loan funds to the loan recipient, or upon
3.8.2
Upon completion of the DWSIRLF audit (or if an audit is not performed, following
3.8.3
Unless, within 30 days after the date of the above final determination, the loan
3.8.4
Should an appeal be submitted in accordance with Rule 3.8.3 above, the disputes
3.8.5
Upon receipt of an executed final loan agreement from the loan recipient, repayment
3.8.6
Upon such execution and return, the Department will transmit a copy to the loan
3.9.1
Payments from the DWSIRLF may be made to DWSIRLF loan recipients under the
3.10.1
Interest on amounts paid to the loan recipient shall commence on the last
3.10.2
The amount of interest accrued between the date established in Rule 3.10.1 above
3.10.3
The loan repayment period will commence as soon as practical after transmittal of
3.10.4
Repayments are to be made by counties on a semi-annual basis through homestead
3.10.5
The repayment interest rate and the frequency of interest compounding will be as